CAPM Practice: Determine how to prepare and execute task management steps

Question 21 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

What does 'swarming' mean in agile task management?
Show answer & explanation

Correct answer: Multiple team members working together on a single task to complete it faster

Explanation

Swarming is when multiple team members collaborate on a single item to complete it faster, especially when it's blocked or at risk. It prioritizes completing work over starting new work, reducing WIP.

**Why not B:** Swarming is a collaborative practice within a team, not a competition between teams. Having multiple teams race to finish the same feature would duplicate effort and waste capacity.

**Why not C:** Estimating with the Fibonacci sequence describes relative estimation techniques such as Planning Poker, not swarming. Swarming concerns how work gets completed, not how it is sized.

**Why not D:** A daily meeting to review task progress describes the daily standup, not swarming. Swarming is team members jointly working on an item, not a status review event.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).

Share: