CAPM Practice: Determine how to prepare and execute task management steps

Question 20 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

In a Scrum team, who is responsible for deciding which tasks to take on during an iteration?
Show answer & explanation

Correct answer: The development team self-organizes and pulls work based on capacity and skill

Explanation

In Scrum, the development team self-organizes — team members pull work items they can best contribute to rather than having work assigned top-down. This promotes ownership and leverages team members' expertise.

**Why not B:** The product owner prioritizes the backlog but does not assign individual tasks.

**Why not C:** Top-down task assignment undermines the team's self-organization.

**Why not D:** The Scrum Master is a servant leader who facilitates, not someone who distributes work.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).