CAPM Practice: Determine how to prepare and execute task management steps

Question 22 of 60 in Determine how to prepare and execute task management steps

How does a team 'pull' work in a Kanban system?
Show answer & explanation

Correct answer: Team members take work from the top of the backlog only when they have capacity, respecting WIP limits

Explanation

Kanban uses a pull system — work is pulled by team members when they have capacity (and WIP limits allow), rather than being pushed by management. This prevents overloading and respects the team's capacity.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).