CAPM Practice: Determine how to prepare and execute task management steps
Question 19 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The team's commitment to adaptive practices has eroded; a team-facilitated process reset is needed, re-establishing the purpose of each board element, re-committing to WIP limits and DoD, and implementing accountability mechanisms like daily board review in standups
Explanation
Board deterioration is a symptom of eroded practice commitment, not a tool failure. A process reset (facilitated by the Scrum Master) should: (1) review what each board element is for and why it matters; (2) clean up the board collaboratively; (3) re-agree on WIP limits, DoD, and update responsibilities; (4) establish simple accountability mechanisms (e.g., each standup includes a 60-second board review). The issue is team discipline and shared ownership, not the tool.
**Why not A:** Replacing the Scrum Master blames one individual for what is a shared team problem. Keeping the board current and honoring WIP limits is the collective responsibility of a self-organizing team, and removing the Scrum Master would not restore the team's commitment to its own practices.
**Why not C:** Switching frameworks does not address the root cause. The team has stopped following practices it already agreed to—updating cards, enforcing WIP limits, keeping the board clean—and those same discipline gaps would follow the team into any new framework.
**Why not D:** The tool is not the problem. Moving from a digital to a physical board does not by itself restore WIP limit enforcement or consistent updates; without renewed team commitment, a physical board would deteriorate in the same way.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).