CAPM Practice: Determine how to prepare and execute task management steps
Question 18 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Address the critical production bug immediately — most teams have an expedite path or will drop lowest-priority sprint items to make capacity for critical bugs
Explanation
Critical production issues affecting all users take priority over sprint commitments. Most adaptive teams have an expedite or 'emergency' swim lane for exactly this scenario. Handling approaches include: using a designated capacity for urgent issues (e.g., 20% of sprint capacity reserved for production support) or dropping lowest-priority sprint items to make room. The sprint goal guides the decision — if the bug doesn't compromise the sprint goal, some items might continue in parallel.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free