CAPM Practice: Determine how to plan project iterations
Question 46 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Use a rolling average of recent velocity and factor in known capacity changes
Explanation
High velocity variance suggests unstable team capacity or estimation issues. Using a rolling average (e.g., last 3 iterations) while accounting for known changes (vacations, new team members) provides a more reliable planning basis.
**Why not B:** Planning to the highest historical velocity (50 points) is an optimistic fallacy — it assumes exceptional conditions will repeat and ignores the variance that already makes the team's output unreliable. Consistently over-committing leads to incomplete work at the end of iterations, team stress, and erodes stakeholder trust in the team's estimates over time.
**Why not C:** Committing to zero points is neither practical nor useful. While it is important not to over-commit during unstable periods, teams must continue delivering value each iteration. Zero-point commitments would halt product progress and provide no useful velocity signal to help stabilize future planning.
**Why not D:** Velocity and capacity planning are development team responsibilities — the product owner's role is to prioritize what to build, not to determine how much the team can deliver. Delegating capacity decisions to the PO violates the team's self-organizing principle and would likely produce commitments that ignore actual technical constraints and team availability.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).