CAPM Practice: Determine how to plan project iterations
Question 47 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Setting a fixed duration for an activity or iteration that cannot be extended
Explanation
A timebox is a fixed period of time for an activity. Iterations are timeboxed — if the team doesn't complete all planned work, the iteration ends anyway and incomplete items return to the backlog.
**Why not A:** Timeboxing is a scheduling technique applied to activities and iterations — it has nothing to do with restricting individual team members' working hours. Agile teams are self-organizing and autonomous in how they manage their personal schedules. Conflating timeboxing with shift-based work scheduling reflects a fundamental misunderstanding of the concept.
**Why not C:** Limiting backlog size is a backlog management practice, not a timeboxing concept. Timeboxing governs the duration of events and iterations, not the quantity of items in a list. The product owner manages backlog size through prioritization and grooming, independent of any timebox.
**Why not D:** The timing consistency of daily standups is a convention that supports predictability and team habit formation, but it is not what "timebox" means. Timeboxing refers to fixing the total duration of an activity — a standup is itself timeboxed to 15 minutes, regardless of what time of day it begins.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).