CAPM Practice: Determine how to plan project iterations

Question 45 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

When planning iterations for a project with multiple dependent teams, what technique helps coordinate dependencies?
Show answer & explanation

Correct answer: Using a Scrum of Scrums or similar cross-team coordination mechanism alongside iteration planning

Explanation

Scrum of Scrums (or similar mechanisms like cross-team planning in SAFe) coordinates dependencies across teams, ensuring they align on shared goals and address cross-team impediments during multi-team iteration planning.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).