CAPM Practice: Determine how to plan project iterations

Question 44 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

In Scaled Agile Framework (SAFe), what replaces individual team iterations at the program level?
Show answer & explanation

Correct answer: Program Increments (PI) with PI Planning events

Explanation

SAFe uses Program Increments (PIs) — typically 8-12 week periods — with PI Planning events where multiple teams align on objectives, dependencies, and risks across the program increment.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).