In Scaled Agile Framework (SAFe), what replaces individual team iterations at the program level?
Show answer & explanation
Correct answer: Program Increments (PI) with PI Planning events
Explanation
SAFe uses Program Increments (PIs) — typically 8-12 week periods — with PI Planning events where multiple teams align on objectives, dependencies, and risks across the program increment.