CAPM Practice: Determine how to plan project iterations
Question 43 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Release planning forecasts a longer-term roadmap across multiple iterations, while iteration planning commits to work for a single iteration
Explanation
Release planning takes a longer view, forecasting which features can be delivered across multiple iterations. Iteration planning zooms in to specific work committed for one iteration. Both work together for effective adaptive project management.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).