CAPM Practice: Determine how to plan project iterations
Question 32 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: To select and commit to a set of work items the team will complete during the iteration
Explanation
Iteration planning is primarily about selecting backlog items the team commits to completing within the timeboxed iteration, aligning on goals and creating a plan to achieve them.
**Why not A:** Iteration planning covers only the upcoming iteration, and agile teams self-organize rather than having tasks assigned for the entire project.
**Why not B:** Agile teams do not document all requirements up front for approval; the backlog is progressively elaborated.
**Why not C:** Iteration planning does not set quarterly budgets; it selects work for the timeboxed iteration.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).