CAPM Practice: Determine how to plan project iterations
Question 31 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A statement of purpose that explains the value the sprint will deliver and could still be achieved even if some specific stories are not completed
Explanation
A good sprint goal expresses the PURPOSE and VALUE of the sprint, not just a task list. For example: 'Enable users to complete the checkout process end-to-end' is a sprint goal — the team might accomplish it through multiple stories, but the goal guides decisions if stories take longer than expected. A goal-oriented sprint allows the team to make trade-offs (skip a story, add a workaround) while staying aligned with the goal's intent.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free