CAPM Practice: Determine how to plan project iterations
Question 31 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A statement of purpose that explains the value the sprint will deliver and could still be achieved even if some specific stories are not completed
Explanation
A good sprint goal expresses the PURPOSE and VALUE of the sprint, not just a task list. For example: 'Enable users to complete the checkout process end-to-end' is a sprint goal — the team might accomplish it through multiple stories, but the goal guides decisions if stories take longer than expected. A goal-oriented sprint allows the team to make trade-offs (skip a story, add a workaround) while staying aligned with the goal's intent.
**Why not A:** A sprint goal is not a management objective expressed in financial terms. It describes the value and purpose the team will deliver in this sprint, which guides the team's day-to-day trade-offs rather than reporting a monetary target.
**Why not C:** A list of sprint backlog items is exactly the weak goal the product owner already has ('complete stories X, Y, and Z'). A task list gives the team no shared purpose to guide decisions when work takes longer than expected.
**Why not D:** A commitment to complete all backlog items turns the goal back into a task list and removes the flexibility a goal provides. The team commits to the sprint goal, while the specific items needed to reach it can be negotiated as work emerges.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).