In Scrum, which artifact is used to plan what will be accomplished during a Sprint?
Show answer & explanation

Correct answer: Sprint Backlog

Explanation

The Sprint Backlog is the set of Product Backlog items selected for the Sprint plus a plan for delivering the product Increment and realizing the Sprint Goal.

**Why not A:** A burndown chart tracks remaining work during the Sprint; it is not the plan of what will be accomplished.

**Why not B:** The Definition of Done describes the quality standard for the Increment, not the work planned for the Sprint.

**Why not D:** The Product Backlog is the ordered list for the whole product; only the items selected for the Sprint form the Sprint Backlog.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).