CAPM Practice: Determine how to plan project iterations
Question 33 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Sprint Backlog
Explanation
The Sprint Backlog is the set of Product Backlog items selected for the Sprint plus a plan for delivering the product Increment and realizing the Sprint Goal.
**Why not A:** A burndown chart tracks remaining work during the Sprint; it is not the plan of what will be accomplished.
**Why not B:** The Definition of Done describes the quality standard for the Increment, not the work planned for the Sprint.
**Why not D:** The Product Backlog is the ordered list for the whole product; only the items selected for the Sprint form the Sprint Backlog.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free