CAPM Practice: Determine how to plan project iterations

Question 41 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

Which technique helps teams estimate the effort needed for user stories during iteration planning?
Show answer & explanation

Correct answer: Planning poker (estimation poker)

Explanation

Planning poker is a consensus-based estimation technique where team members use cards to estimate the relative effort of user stories. It promotes discussion and reduces anchoring bias.

**Why not A:** A Gantt chart displays the schedule over time; it is not a technique for estimating story effort.

**Why not B:** The critical path method analyzes activity sequences to determine schedule duration; it does not estimate user story effort.

**Why not D:** Earned value analysis measures cost and schedule performance against a baseline; it is not an estimation technique.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).