CAPM Practice: Determine how to plan project iterations
Question 41 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Planning poker (estimation poker)
Explanation
Planning poker is a consensus-based estimation technique where team members use cards to estimate the relative effort of user stories. It promotes discussion and reduces anchoring bias.
**Why not A:** A Gantt chart displays the schedule over time; it is not a technique for estimating story effort.
**Why not B:** The critical path method analyzes activity sequences to determine schedule duration; it does not estimate user story effort.
**Why not D:** Earned value analysis measures cost and schedule performance against a baseline; it is not an estimation technique.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free