What is the purpose of a 'Sprint Goal' in Scrum iteration planning?
Show answer & explanation

Correct answer: To provide a single objective that gives the team focus and flexibility during the Sprint

Explanation

The Sprint Goal is a brief, shared objective for the Sprint that provides the team with focus and direction. It gives the team flexibility in how they achieve it while maintaining a clear purpose.

**Why not A:** The Sprint Goal is a team commitment, not a record of a project manager's expectations.

**Why not C:** It is an objective, not a tally of story points per developer.

**Why not D:** The task-level plan lives in the Sprint Backlog, not the Sprint Goal.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).