Question 42 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

A development team discovers mid-iteration that a key dependency won't be available as planned. What is the appropriate agile response?
Show answer & explanation

Correct answer: Adapt by pulling in alternative backlog items and addressing the dependency in planning

Explanation

Agile teams adapt to impediments by pulling alternative ready backlog items into the iteration and addressing the dependency issue through the Scrum Master or team lead, maintaining iteration flow.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).