CAPMMedium
CAPM Practice: Determine how to plan project iterations
Question 42 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
A development team discovers mid-iteration that a key dependency won't be available as planned. What is the appropriate agile response?
Show answer & explanation
Correct answer: Adapt by pulling in alternative backlog items and addressing the dependency in planning
Explanation
Agile teams adapt to impediments by pulling alternative ready backlog items into the iteration and addressing the dependency issue through the Scrum Master or team lead, maintaining iteration flow.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free