CAPM Practice: Determine how to plan project iterations
Question 3 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A short statement of what value the sprint will deliver to the customer
Explanation
A sprint goal is a concise statement of the value or objective the sprint will achieve. It provides focus and cohesion: even if some individual items are not completed, if the sprint goal is achieved, the sprint was successful. The sprint goal guides the team's decisions during the sprint and communicates the sprint's purpose to stakeholders.
**Why not A:** The sprint goal is not a promise to finish every sprint backlog item. The sprint backlog can be renegotiated as the team learns, and the sprint can still succeed if the goal is met even when some individual items are not completed.
**Why not B:** The total story points planned reflects the team's forecast of how much work fits in the sprint, not the purpose of that work. A sprint goal describes the value to be delivered, not the volume of work.
**Why not D:** A sprint is timeboxed, but the sprint goal is not a date or deadline. The timing of sprint events is set by the sprint cadence, while the goal states what the sprint is meant to achieve.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free