CAPM Practice: Determine how to plan project iterations
Question 3 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A short statement of what value the sprint will deliver to the customer
Explanation
A sprint goal is a concise statement of the value or objective the sprint will achieve. It provides focus and cohesion: even if some individual items are not completed, if the sprint goal is achieved, the sprint was successful. The sprint goal guides the team's decisions during the sprint and communicates the sprint's purpose to stakeholders.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free