CAPM Practice: Determine how to plan project iterations
Question 4 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Remove lower-priority items from the sprint backlog until the commitment aligns with team capacity
Explanation
Overcommitting to sprint work sets the team up for failure and undermines trust. The team should remove lower-priority items (in consultation with the product owner) until the sprint backlog aligns with realistic capacity. Better to deliver a focused sprint goal fully than to overcommit and deliver partially — predictability builds stakeholder trust.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free