CAPM Practice: Determine how to plan project iterations

Question 4 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

During sprint planning, the team estimates the sprint backlog items and realizes they have committed to 20% more than their average velocity. What should they do?
Show answer & explanation

Correct answer: Remove lower-priority items from the sprint backlog until the commitment aligns with team capacity

Explanation

Overcommitting to sprint work sets the team up for failure and undermines trust. The team should remove lower-priority items (in consultation with the product owner) until the sprint backlog aligns with realistic capacity. Better to deliver a focused sprint goal fully than to overcommit and deliver partially — predictability builds stakeholder trust.

**Why not A:** Adding team members does not resolve the overcommitment and typically lowers short-term velocity because of onboarding and coordination overhead. Team composition is not adjusted sprint by sprint to absorb an oversized backlog — the team should right-size the commitment instead.

**Why not B:** The team, together with the product owner, owns the sprint backlog and is self-managing. Escalating a routine capacity mismatch to the sponsor removes ownership from the team and delays a decision that belongs in sprint planning.

**Why not C:** Knowingly committing beyond average velocity sets the team up for failure, encourages burnout and quality shortcuts, and undermines predictability. Sustainable pace is an agile principle — overloading a sprint does not reliably raise performance.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).