Skip to content
CAPMEasy

CAPM Practice: Determine how to plan project iterations

Question 2 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

A sprint in Scrum is best described as:
Show answer & explanation

Correct answer: A fixed-length time box (typically 1-4 weeks) within which a potentially releasable increment is produced

Explanation

A sprint is a fixed-length, time-boxed event (1-4 weeks, typically 2 weeks) during which the team works to complete the sprint backlog and produce a Done increment. Sprints have a fixed start and end date; the sprint ends on schedule regardless of completion. Each sprint is a complete mini-project cycle: plan, execute, review, retrospect.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free