Skip to content
CAPMEasy

CAPM Practice: Determine how to plan project iterations

Question 27 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

An iteration in an adaptive project ends. The team has completed 7 out of 8 planned stories, and all 7 meet the Definition of Done. What is delivered?
Show answer & explanation

Correct answer: A potentially shippable increment consisting of the 7 completed stories if they meet the sprint goal

Explanation

In adaptive approaches, the increment is what is Done — not what was planned. The 7 completed stories that meet the Definition of Done constitute the sprint increment. If these 7 stories meet the sprint goal, the sprint was successful. The 8th story returns to the product backlog for re-prioritization. Delivering incomplete work or reducing quality violates the Definition of Done.

**Why not B:** The 8th story is not done, so it cannot be delivered as part of the increment. Adaptive teams do not extend the iteration or push unfinished work into the increment; the incomplete story returns to the product backlog for re-prioritization.

**Why not C:** Delivering a story at reduced quality violates the Definition of Done. The increment must only contain work that meets the agreed quality standard, regardless of the original sprint plan.

**Why not D:** The sprint goal is an objective, not a requirement that every planned story be completed. The 7 Done stories form a usable increment, and if they meet the sprint goal, the iteration delivered value.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free