CAPM Practice: Determine how to plan project iterations
Question 27 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A potentially shippable increment consisting of the 7 completed stories if they meet the sprint goal
Explanation
In adaptive approaches, the increment is what is Done — not what was planned. The 7 completed stories that meet the Definition of Done constitute the sprint increment. If these 7 stories meet the sprint goal, the sprint was successful. The 8th story returns to the product backlog for re-prioritization. Delivering incomplete work or reducing quality violates the Definition of Done.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free