CAPM Practice: Determine how to plan project iterations

Question 26 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team has been working for 3 months and their velocity is stable at 40 story points per sprint (2-week sprints). The product owner wants to know if they can add 5 new team members to double velocity and halve delivery time. What is the MOST accurate advice?
Show answer & explanation

Correct answer: Adding 5 team members will likely temporarily decrease velocity as new members onboard, learn the codebase, and disrupt established team dynamics; eventual velocity may increase but the 'double velocity immediately' expectation is unrealistic

Explanation

This is Brooks' Law in action: 'Adding manpower to a late software project makes it later.' Adding 5 people to a 5-person team will initially hurt velocity: onboarding time, communication overhead (new communication paths = N(N-1)/2), knowledge transfer, and process disruption. Eventually the expanded team may reach higher velocity — but not immediately, and not necessarily double the original velocity. The PM should educate the PO on realistic expectations.

**Why not A:** Team size is not frozen in adaptive projects — teams can change composition when there is a valid reason. The real issue is setting realistic expectations about how adding members will affect velocity and delivery time, not forbidding any change.

**Why not B:** Velocity does not scale linearly with headcount. New members need onboarding and knowledge transfer, communication paths increase sharply, and established team dynamics are disrupted, so doubling team size will not double velocity proportionally.

**Why not C:** Adding team members is not always the best way to recover schedule — as Brooks' Law warns, it often slows a team down in the short term. Other levers such as backlog reprioritization or scope adjustment should be considered.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).