CAPM Practice: Determine how to plan project iterations
Question 26 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Adding 5 team members will likely temporarily decrease velocity as new members onboard, learn the codebase, and disrupt established team dynamics; eventual velocity may increase but the 'double velocity immediately' expectation is unrealistic
Explanation
This is Brooks' Law in action: 'Adding manpower to a late software project makes it later.' Adding 5 people to a 5-person team will initially hurt velocity: onboarding time, communication overhead (new communication paths = N(N-1)/2), knowledge transfer, and process disruption. Eventually the expanded team may reach higher velocity — but not immediately, and not necessarily double the original velocity. The PM should educate the PO on realistic expectations.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free