CAPM Practice: Determine how to plan project iterations
An adaptive team has been working for 3 months and their velocity is stable at 40 story points per sprint (2-week sprints). The product owner wants to know if they can add 5 new team members to double velocity and halve delivery time. What is the MOST accurate advice?
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).