CAPM Practice: Determine how to plan project iterations

Question 26 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team has been working for 3 months and their velocity is stable at 40 story points per sprint (2-week sprints). The product owner wants to know if they can add 5 new team members to double velocity and halve delivery time. What is the MOST accurate advice?
Show answer & explanation

Correct answer: Adding 5 team members will likely temporarily decrease velocity as new members onboard, learn the codebase, and disrupt established team dynamics; eventual velocity may increase but the 'double velocity immediately' expectation is unrealistic

Explanation

This is Brooks' Law in action: 'Adding manpower to a late software project makes it later.' Adding 5 people to a 5-person team will initially hurt velocity: onboarding time, communication overhead (new communication paths = N(N-1)/2), knowledge transfer, and process disruption. Eventually the expanded team may reach higher velocity — but not immediately, and not necessarily double the original velocity. The PM should educate the PO on realistic expectations.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).