CAPM Practice: Determine how to plan project iterations
Question 28 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The new story is estimated to require roughly 2-3 times more effort/complexity than the 3-point reference story
Explanation
Story points are relative estimates — they measure size/complexity/effort relative to other stories, not absolute time or cost. An 8-point story is roughly 2-3 times larger (complex, uncertain, or effortful) than the 3-point reference story. The team's velocity (historical points per sprint) converts relative sizes into delivery forecasts — but no individual story is tied to specific hours.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free