CAPM Practice: Determine how to plan project iterations
Question 28 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The new story is estimated to require roughly 2-3 times more effort/complexity than the 3-point reference story
Explanation
Story points are relative estimates — they measure size/complexity/effort relative to other stories, not absolute time or cost. An 8-point story is roughly 2-3 times larger (complex, uncertain, or effortful) than the 3-point reference story. The team's velocity (historical points per sprint) converts relative sizes into delivery forecasts — but no individual story is tied to specific hours.
**Why not A:** Story points are not a currency measure. An 8-point estimate says nothing about dollar cost; any cost forecast would have to be derived separately from team capacity and velocity, not read directly from the point value.
**Why not B:** Story points do not convert directly into calendar days. Delivery forecasts come from the team's velocity across sprints, not from equating one point with one day of work.
**Why not D:** Story points are deliberately abstracted from hours. An 8-point story does not mean exactly 8 hours — relative estimation avoids that kind of false precision, and the number only has meaning in comparison to other stories such as the 3-point reference.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).