CAPM Practice: Determine how to plan project iterations

Question 28 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

A scrum team is using relative estimation and has a 'reference story' of 3 story points for a well-understood task. They estimate a new story as '8 points.' This means:
Show answer & explanation

Correct answer: The new story is estimated to require roughly 2-3 times more effort/complexity than the 3-point reference story

Explanation

Story points are relative estimates — they measure size/complexity/effort relative to other stories, not absolute time or cost. An 8-point story is roughly 2-3 times larger (complex, uncertain, or effortful) than the 3-point reference story. The team's velocity (historical points per sprint) converts relative sizes into delivery forecasts — but no individual story is tied to specific hours.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).