CAPM Practice: Determine how to plan project iterations
Question 34 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The amount of work a team completes per iteration, used to forecast future iterations
Explanation
Velocity measures how much work (story points or other units) a team completes in a single iteration. It helps teams forecast how much work they can commit to in future iterations.
**Why not A:** Velocity is not a measure of individual typing or coding speed; it measures the team's completed work per iteration.
**Why not B:** Defects found per day is a quality metric, not velocity.
**Why not C:** Time to deploy a release is a lead time or deployment measure, not velocity.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).