Skip to content
CAPMEasy

CAPM Practice: Determine how to plan project iterations

Question 34 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

What does 'velocity' measure in agile iteration planning?
Show answer & explanation

Correct answer: The amount of work a team completes per iteration, used to forecast future iterations

Explanation

Velocity measures how much work (story points or other units) a team completes in a single iteration. It helps teams forecast how much work they can commit to in future iterations.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free