CAPM Practice: Determine how to plan project iterations
Question 35 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Review and refine the prioritized backlog to select items for the iteration
Explanation
Iteration planning typically begins with reviewing the prioritized backlog (refined during backlog grooming) and selecting the highest-priority items the team can commit to completing within the iteration.
**Why not B:** Tasks come after items are selected, and team members pull work rather than being assigned it.
**Why not C:** Status reporting is not part of iteration planning.
**Why not D:** Detailed upfront specifications are not the first step; detail emerges as selected items are discussed.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).