CAPM Practice: Determine how to plan project iterations
Question 29 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Ensure the team understands the process, the event remains productive, and decisions are made within the time box
Explanation
The Scrum Master facilitates the sprint planning event — ensuring the process runs effectively, time is used well, decisions are reached, and the team leaves with a clear sprint goal and sprint backlog. The SM does not assign work (team self-organizes) or set the sprint goal (PO and team collaborate on this). The SM is a process facilitator, not a decision-maker in sprint planning.
**Why not A:** Estimates are produced by the team members who will do the work, not by the Scrum Master. The SM may facilitate the estimation conversation, but does not estimate the backlog items.
**Why not B:** The sprint goal is crafted collaboratively by the product owner and the team during sprint planning. The SM facilitates that conversation but does not decide the goal.
**Why not C:** The team self-organizes and decides who takes on which work. Assigning stories to individuals undermines self-organization and is not the SM's role.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free