CAPM Practice: Determine how to plan project iterations
Question 29 of 61 in Determine how to plan project iterations
Show answer & explanation
Correct answer: Ensure the team understands the process, the event remains productive, and decisions are made within the time box
Explanation
The Scrum Master facilitates the sprint planning event — ensuring the process runs effectively, time is used well, decisions are reached, and the team leaves with a clear sprint goal and sprint backlog. The SM does not assign work (team self-organizes) or set the sprint goal (PO and team collaborate on this). The SM is a process facilitator, not a decision-maker in sprint planning.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free