CAPM Practice: Determine how to plan project iterations
Question 30 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Inform the product owner of the situation, identify options (de-scope lower-priority stories, negotiate sprint goal adjustment), and maintain transparency
Explanation
Transparency is a core Scrum pillar. When mid-sprint discoveries reveal a commitment gap, the team should immediately inform the product owner. Together, they can decide: reduce sprint scope (move lower-priority stories back to backlog), adjust the sprint goal to reflect what can actually be delivered, or take other actions. Hiding the problem until the review destroys trust and delays recovery options.
**Why not A:** Lowering quality to finish more stories violates the Definition of Done. Quality is not negotiable in Scrum; scope is what flexes. Work that does not meet the agreed quality standard is not a done increment and creates hidden technical debt.
**Why not C:** Hiding the problem until the sprint review violates transparency and removes the product owner's chance to make scope decisions while there is still time to act. Surprising stakeholders at the review damages trust and eliminates recovery options.
**Why not D:** Routine overtime to cover an estimation gap is unsustainable and conflicts with the agile principle of a sustainable pace. It also hides the real capacity problem from the product owner instead of making it visible so priorities can be adjusted.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).