CAPM Practice: Determine how to plan project iterations
Question 30 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Inform the product owner of the situation, identify options (de-scope lower-priority stories, negotiate sprint goal adjustment), and maintain transparency
Explanation
Transparency is a core Scrum value. When mid-sprint discoveries reveal a commitment gap, the team should immediately inform the product owner. Together, they can decide: reduce sprint scope (move lower-priority stories back to backlog), adjust the sprint goal to reflect what can actually be delivered, or take other actions. Hiding the problem until the review destroys trust and delays recovery options.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free