CAPM Practice: Determine how to plan project iterations

Question 30 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

A team is mid-sprint and realizes that completing the sprint goal will require more work than estimated. The team should:
Show answer & explanation

Correct answer: Inform the product owner of the situation, identify options (de-scope lower-priority stories, negotiate sprint goal adjustment), and maintain transparency

Explanation

Transparency is a core Scrum value. When mid-sprint discoveries reveal a commitment gap, the team should immediately inform the product owner. Together, they can decide: reduce sprint scope (move lower-priority stories back to backlog), adjust the sprint goal to reflect what can actually be delivered, or take other actions. Hiding the problem until the review destroys trust and delays recovery options.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).