CAPM Practice: Determine how to plan project iterations

Question 39 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

In Kanban, what concept replaces time-boxed iterations for planning and managing flow?
Show answer & explanation

Correct answer: Work-in-progress (WIP) limits and continuous flow

Explanation

Kanban uses WIP limits and continuous flow rather than time-boxed iterations. Work items are pulled from the backlog as capacity permits, with WIP limits preventing overloading the system.

**Why not A:** Release trains are a scaled agile (SAFe) construct for synchronizing multiple teams on a fixed planning cadence. They are not the Kanban mechanism that replaces time-boxed iterations.

**Why not B:** Milestone gates are a predictive, phase-gate governance mechanism. Kanban manages work through continuous flow, not through gated phases.

**Why not D:** Sprint goals belong to Scrum's time-boxed sprints—exactly the iteration structure that Kanban does not use.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).