CAPM Practice: Determine how to plan project iterations
Question 39 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Work-in-progress (WIP) limits and continuous flow
Explanation
Kanban uses WIP limits and continuous flow rather than time-boxed iterations. Work items are pulled from the backlog as capacity permits, with WIP limits preventing overloading the system.
**Why not A:** Release trains are a scaled agile (SAFe) construct for synchronizing multiple teams on a fixed planning cadence. They are not the Kanban mechanism that replaces time-boxed iterations.
**Why not B:** Milestone gates are a predictive, phase-gate governance mechanism. Kanban manages work through continuous flow, not through gated phases.
**Why not D:** Sprint goals belong to Scrum's time-boxed sprints—exactly the iteration structure that Kanban does not use.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).