CAPM Practice: Determine how to plan project iterations

Question 38 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

What is a 'Definition of Ready' and how does it affect iteration planning?
Show answer & explanation

Correct answer: Criteria that user stories must meet before the team can commit to working on them in an iteration

Explanation

The Definition of Ready specifies the criteria (acceptance criteria, estimated, no blocking dependencies) a backlog item must meet before the team can pull it into an iteration. It prevents poorly defined work from entering the iteration plan.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).