CAPM Practice: Determine how to plan project iterations
Question 38 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Criteria that user stories must meet before the team can commit to working on them in an iteration
Explanation
The Definition of Ready specifies the criteria (acceptance criteria, estimated, no blocking dependencies) a backlog item must meet before the team can pull it into an iteration. It prevents poorly defined work from entering the iteration plan.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free