CAPM Practice: Determine how to plan project iterations
Question 7 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The product backlog contains all work for the entire product; the sprint backlog contains the subset selected for the current sprint
Explanation
The product backlog is the complete, prioritized list of all work for the product — maintained by the product owner. The sprint backlog is a subset: the specific items selected for the current sprint, plus the team's plan for accomplishing them. The sprint backlog is owned by the development team for the duration of the sprint.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).