Skip to content
CAPMMedium

CAPM Practice: Determine how to plan project iterations

Question 7 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

What is the difference between a 'product backlog' and a 'sprint backlog'?
Show answer & explanation

Correct answer: The product backlog contains all work for the entire product; the sprint backlog contains the subset selected for the current sprint

Explanation

The product backlog is the complete, prioritized list of all work for the product — maintained by the product owner. The sprint backlog is a subset: the specific items selected for the current sprint, plus the team's plan for accomplishing them. The sprint backlog is owned by the development team for the duration of the sprint.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free