CAPM Practice: Determine how to plan project iterations
Question 7 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The product backlog contains all work for the entire product; the sprint backlog contains the subset selected for the current sprint
Explanation
The product backlog is the complete, prioritized list of all work for the product — maintained by the product owner. The sprint backlog is a subset: the specific items selected for the current sprint, plus the team's plan for accomplishing them. The sprint backlog is owned by the development team for the duration of the sprint.
**Why not A:** This reverses the accountabilities. The product owner manages the product backlog, while the development team owns the sprint backlog and its plan for completing the selected work during the sprint.
**Why not C:** They are separate artifacts with different scopes and owners. The product backlog persists for the life of the product, while a new sprint backlog is created at each sprint planning from items selected out of the product backlog.
**Why not D:** The product backlog is the larger artifact because it contains all known work for the product. The sprint backlog may break selected items into detailed tasks, but it covers only the work chosen for a single sprint.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).