CAPM Practice: Determine how to plan project iterations
Question 8 of 61 in Determine how to plan project iterations
Show answer & explanation
Correct answer: Using the previous iteration's velocity as the starting estimate for the next iteration's capacity
Explanation
'Yesterday's weather' is a simple planning heuristic: the team uses its most recent sprint's velocity as the planning assumption for the next sprint. If the team averaged 35 story points last sprint, they plan for approximately 35 story points next sprint. This empirical approach is more reliable than elaborate capacity calculations, especially for stable, established teams.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).