CAPM Practice: Determine how to plan project iterations
Question 8 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Using the previous iteration's velocity as the starting estimate for the next iteration's capacity
Explanation
'Yesterday's weather' is a simple planning heuristic: the team uses its most recent sprint's velocity as the planning assumption for the next sprint. If the team completed 35 story points last sprint, they plan for approximately 35 story points next sprint. This empirical approach is more reliable than elaborate capacity calculations, especially for stable, established teams.
**Why not B:** 'Yesterday's weather' is not a Scrum ceremony. The event that inspects progress since the previous day is the daily scrum (daily standup), which focuses on progress toward the sprint goal — not on forecasting capacity for the next iteration.
**Why not C:** This is a literal misreading of the metaphor. The term has nothing to do with meteorological data; it refers to relying on the team's own recent empirical performance to predict near-term capacity.
**Why not D:** Estimating from past project analogies is analogous estimating. 'Yesterday's weather' uses the same team's most recent iteration velocity, not comparisons with other or earlier projects.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).