CAPM Practice: Determine how to plan project iterations
Question 6 of 61 in Determine how to plan project iterations
Show answer & explanation
Correct answer: Yes — the Scrum Guide suggests sprint planning should be no more than 8 hours for a one-month sprint, proportionally less for shorter sprints (4 hours for a 2-week sprint)
Explanation
The Scrum Guide suggests sprint planning is time-boxed to a maximum of 8 hours for a one-month sprint, proportionally less for shorter sprints. For a 2-week (half-month) sprint, a maximum of 4 hours is appropriate. This 4-hour planning session is within the guideline and is not excessive for setting up a 2-week sprint effectively.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free