CAPM Practice: Determine how to plan project iterations

Question 6 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

A team's sprint planning session runs 4 hours for a 2-week sprint. Is this appropriate?
Show answer & explanation

Correct answer: Yes — the Scrum Guide suggests sprint planning should be no more than 8 hours for a one-month sprint, proportionally less for shorter sprints (4 hours for a 2-week sprint)

Explanation

The Scrum Guide suggests sprint planning is time-boxed to a maximum of 8 hours for a one-month sprint, proportionally less for shorter sprints. For a 2-week (half-month) sprint, a maximum of 4 hours is appropriate. This 4-hour planning session is within the guideline and is not excessive for setting up a 2-week sprint effectively.

**Why not B:** Sprint planning is a time-boxed event. Letting it run as long as needed regardless of sprint length ignores the Scrum Guide's maximum of 8 hours for a one-month sprint and risks eating into the time the team needs for delivery.

**Why not C:** There is no universal 2-hour maximum for sprint planning. The time-box scales with sprint length, so up to 4 hours is within the guideline for a 2-week sprint.

**Why not D:** A 30-minute cap is far shorter than the Scrum Guide time-box and would rarely give the team enough time to define a sprint goal, select backlog items, and plan how to deliver them.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).