CAPM Practice: Determine how to plan project iterations
Question 5 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Prioritized backlog items, team capacity, and technical dependencies
Explanation
Effective iteration planning requires: prioritized backlog items (what to work on), team capacity (how much can be done), and technical dependencies (what constraints exist between items). Other considerations include team availability (vacations, training), definition of done criteria, and risks associated with specific items. These factors together determine what can realistically be committed to in the iteration.
**Why not B:** Stakeholder feedback shapes backlog prioritization, but it is only one input. Planning from the most recent feedback alone ignores team capacity, dependencies, and the overall priority order of the backlog.
**Why not C:** Adaptive teams are self-organizing and commit to work together. The project manager's assignment preferences are not an input to iteration planning.
**Why not D:** Budget is usually set at a higher level, not decided iteration by iteration. Iteration planning focuses on what the team can deliver given priority and capacity, not on a per-iteration funding allocation.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).