Skip to content
CAPMEasy

CAPM Practice: Determine how to plan project iterations

Question 5 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

Iteration planning in an adaptive project considers which inputs?
Show answer & explanation

Correct answer: Prioritized backlog items, team capacity, and technical dependencies

Explanation

Effective iteration planning requires: prioritized backlog items (what to work on), team capacity (how much can be done), and technical dependencies (what constraints exist between items). Other considerations include team availability (vacations, training), definition of done criteria, and risks associated with specific items. These factors together determine what can realistically be committed to in the iteration.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free