CAPM Practice: Determine how to plan project iterations
Question 36 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Analyze root causes of incomplete work and adjust future commitments based on actual velocity
Explanation
When teams consistently under-deliver, they should inspect and adapt — analyzing why work isn't completed and using actual velocity data to make more realistic commitments in future iterations.
**Why not B:** Adding team members may increase capacity over time, but it introduces new complexity — onboarding overhead, communication costs, and temporary productivity dips (Brooks's Law). Before scaling the team, the root cause of underdelivery must be understood; more people will not fix estimation problems, unclear requirements, or process inefficiencies.
**Why not C:** Extending iteration length avoids the problem rather than solving it. Longer iterations reduce feedback cycles and conflict with a core agile principle — the team should learn to plan accurately within a fixed timebox, not stretch the box to accommodate poor planning. The goal is realistic commitment, not more time to fall short.
**Why not D:** Removing or adjusting story points retroactively to improve reported metrics is a form of data manipulation that destroys the integrity of velocity tracking. It provides false signals for future planning and violates the transparency principle of agile. Honest velocity data — even if unflattering — is essential for meaningful improvement.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).