CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 79 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Irina Khoury is working on a project at Quasar Media where a new risk has been identified. The risk register indicates the response strategy is 'mitigate.' What action should Irina take?
Show answer & explanation

Correct answer: Implement actions to reduce the probability or impact of the risk

Explanation

Mitigation is a risk response strategy that involves taking actions to reduce either the probability of the risk occurring or its impact if it does occur. This is different from avoiding (eliminating), transferring, or accepting the risk.

**Why not B:** Transferring the risk to a third party through insurance or contract describes the "transfer" risk response strategy, not mitigation. Transfer shifts the financial impact or responsibility to another party, while mitigation actively reduces probability or impact.

**Why not C:** Accepting the risk and creating a contingency reserve describes the "accept" risk response strategy. Acceptance means acknowledging the risk without proactive action to reduce it, while mitigation involves taking specific actions to reduce the risk's probability or impact.

**Why not D:** Eliminating the risk entirely by changing the project scope describes the "avoid" risk response strategy. Avoidance removes the threat completely, often by changing project plans, while mitigation reduces but does not eliminate the risk.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).