CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 33 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A project benefit
Explanation
The reduction in processing time is an expected outcome or benefit of the project. Benefits are the value or improvements that the organization will realize as a result of the project, and are identified during initiation and benefit planning.
**Why not A:** A constraint is a limiting factor that restricts options, such as a fixed deadline or budget cap. The reduction in processing time is not a limitation — it is a positive outcome the project is expected to deliver.
**Why not B:** A deliverable is a tangible or verifiable output produced by the project, such as a software module or report. The reduction in processing time is an outcome or improvement that results from using the deliverable, not the deliverable itself.
**Why not C:** A risk is an uncertain future event that could affect the project positively or negatively. The processing time reduction is an expected, planned outcome of the project, not an uncertain event. It represents the value the project intends to create.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).