CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 35 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Benefit planning
Explanation
Benefit planning involves identifying and documenting the expected business value and benefits that the project will deliver. This activity typically occurs during project initiation when aligning the project with organizational strategy.
**Why not A:** Risk assessment involves identifying and analyzing potential threats and opportunities that could affect the project. Documenting expected business value is about defining the benefits the project will deliver, not about identifying uncertain future events.
**Why not B:** Quality planning establishes how quality requirements will be met and how deliverables will be verified. While quality contributes to value, documenting expected business value with the sponsor is about defining project benefits, not about setting quality standards.
**Why not D:** Scope definition involves determining what work will be performed and what deliverables will be produced. While scope relates to business value, documenting expected business value specifically aligns with benefit planning, which focuses on the outcomes and value the project will deliver.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).