CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 36 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Conduct the risk review as planned to maintain risk visibility
Explanation
Following the planned risk management strategy is essential for maintaining visibility into project risks. Consistent execution of planned risk reviews ensures emerging risks are identified and managed appropriately, even during busy periods.
**Why not B:** Postponing all risk reviews until the project is less busy creates dangerous gaps in risk monitoring. Busy periods often introduce the most risks, and skipping reviews during these times could allow emerging risks to go undetected and unmanaged.
**Why not C:** Delegating the risk review to the team member who suggested skipping it does not ensure proper risk review quality. Risk reviews require collaborative team participation and project manager leadership, not delegation to someone who has already deprioritized the activity.
**Why not D:** Skipping the review because the team is busy with deliverables undermines the planned risk management strategy. Risk reviews are specifically designed to protect deliverables by identifying threats early, and skipping them increases project exposure during already stressful periods.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).