CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 88 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Vivek Iyer is reviewing how to appropriately respond to different planned strategies at Terraform Urban. Match each project management framework on the left with the appropriate response example on the right. Items: 1. Communication Management Plan 2. Risk Management Plan 3. Quality Management Plan 4. Change Management Plan Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Communication Management Plan → Sending status reports to stakeholders on the scheduled frequency 2. Risk Management Plan → Implementing risk response strategies when trigger conditions are met 3. Quality Management Plan → Conducting inspection and testing as specified in quality standards 4. Change Management Plan → Submitting all change requests through the defined approval process

Explanation

Each planned strategy requires specific execution responses: Communication plans are executed by following the agreed communication schedule and methods. Risk plans are executed by monitoring triggers and implementing planned responses. Quality plans are executed by conducting inspections per quality standards. Change plans are executed by following the formal change control process.

**Why not B:** This option assigns change management activities to the Communication Management Plan and communication activities to the Change Management Plan. Status reports follow the communication plan, while change requests follow the change management plan.

**Why not C:** This option assigns quality activities to the Communication Management Plan, change activities to the Risk Management Plan, communication activities to the Quality Management Plan, and risk activities to the Change Management Plan — all four are mismatched.

**Why not D:** This option assigns risk activities to the Communication Management Plan, quality activities to the Risk Management Plan, change activities to the Quality Management Plan, and communication activities to the Change Management Plan — every response example is matched to the wrong framework.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).