CAPM Practice: Determine how to document project controls for an adaptive project
Question 38 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Program oversight tracks inter-team dependencies, cross-team metrics (like feature flow), and program increment objectives, while team controls focus on iteration-level throughput
Explanation
At the program level, controls focus on cross-team coordination, dependency resolution, program increment progress, and portfolio alignment. Team-level controls focus on iteration throughput, velocity, and sprint goals.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).