Skip to content
CAPMHard

CAPM Practice: Determine how to document project controls for an adaptive project

Question 38 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

In a large-scale agile program, how does program-level oversight differ from team-level adaptive controls?
Show answer & explanation

Correct answer: Program oversight tracks inter-team dependencies, cross-team metrics (like feature flow), and program increment objectives, while team controls focus on iteration-level throughput

Explanation

At the program level, controls focus on cross-team coordination, dependency resolution, program increment progress, and portfolio alignment. Team-level controls focus on iteration throughput, velocity, and sprint goals.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free