CAPM Practice: Determine how to document project controls for an adaptive project
Question 37 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Tracking technical debt as backlog items, setting a debt budget per iteration, and using the Definition of Done to prevent adding new debt
Explanation
Managing technical debt proactively — by tracking it in the backlog, dedicating capacity each iteration, and preventing new debt through a strong Definition of Done — keeps the codebase healthy and sustainable over time.
**Why not A:** Deferring debt to a later project lets it compound in the meantime.
**Why not B:** Annual review is far too infrequent to control accumulating debt.
**Why not C:** Ignoring debt lets it grow and slows future delivery.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).