CAPMEasy
CAPM Practice: Determine how to document project controls for an adaptive project
Question 39 of 60 in Determine how to document project controls for an adaptive project
What is an impediment log in agile project management?
Show answer & explanation
Correct answer: A record of obstacles blocking the team, tracked and resolved by the Scrum Master
Explanation
An impediment log captures blockers preventing the team from progressing. The Scrum Master owns resolving these impediments. It's a lightweight control tool that ensures nothing slows the team for long.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free