CAPM Practice: Determine how to document project controls for an adaptive project
Question 39 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A record of obstacles blocking the team, tracked and resolved by the Scrum Master
Explanation
An impediment log captures blockers preventing the team from progressing. The Scrum Master owns resolving these impediments. It's a lightweight control tool that ensures nothing slows the team for long.
**Why not A:** Charter approval status is a governance matter, not a record of obstacles blocking the team.
**Why not B:** Defects are tracked in the backlog or a defect tracker; the impediment log records blockers to team progress.
**Why not C:** Team member availability belongs in capacity planning, not in a log of obstacles blocking the team.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).