Question 39 of 60 in Determine how to document project controls for an adaptive project

What is an impediment log in agile project management?
Show answer & explanation

Correct answer: A record of obstacles blocking the team, tracked and resolved by the Scrum Master

Explanation

An impediment log captures blockers preventing the team from progressing. The Scrum Master owns resolving these impediments. It's a lightweight control tool that ensures nothing slows the team for long.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).