CAPM Practice: Determine how to document project controls for an adaptive project

Question 40 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

Why is 'just enough documentation' a guiding principle for adaptive project controls?
Show answer & explanation

Correct answer: Because documentation that doesn't add value consumes time that could be spent delivering working product

Explanation

Agile values working software over comprehensive documentation. Documentation should serve a purpose — enabling delivery, maintaining institutional knowledge, or supporting compliance — not be created for its own sake.

**Why not A:** Storage capacity is not the reason; the principle is about value, not space.

**Why not B:** PMI does not prohibit documentation; agile projects create whatever documentation adds value.

**Why not D:** The principle rests on avoiding waste, not on a statistical claim about undocumented teams.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).