CAPM Practice: Determine how to document project controls for an adaptive project
Question 32 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: They make project status and metrics visible to everyone without requiring formal reports
Explanation
Information radiators (task boards, burndown charts, velocity charts) are physical or digital displays that make project information continuously visible to the team and stakeholders, reducing the need for formal status reporting.
**Why not A:** Information radiators do not replace written documentation with verbal communication. They are themselves visual displays of written and graphical information, such as task boards and burndown charts.
**Why not C:** Information radiators exist to create transparency for the team and stakeholders, not to supply management with team-level metrics for individual performance reviews. Using team metrics for performance appraisal can undermine trust and encourage gaming of the numbers.
**Why not D:** PMI does not require information radiators on any project. They are a recommended agile practice that teams adopt for transparency, not a certification mandate.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free