CAPM Practice: Determine how to document project controls for an adaptive project
Question 33 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The time from when a work item is started until it is completed, indicating process efficiency
Explanation
Cycle time measures how long it takes to complete individual work items. Tracking it reveals process efficiency and predictability — stable, short cycle times indicate a well-functioning flow.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free