CAPM Practice: Determine how to document project controls for an adaptive project
Question 33 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The time from when a work item is started until it is completed, indicating process efficiency
Explanation
Cycle time measures how long it takes to complete individual work items. Tracking it reveals process efficiency and predictability — stable, short cycle times indicate a well-functioning flow.
**Why not A:** The number of days in each sprint is the iteration length (timebox), not cycle time. Cycle time is measured per work item, from start to completion, regardless of sprint boundaries.
**Why not C:** Total project duration is a project-level schedule measure, not cycle time. Cycle time focuses on how long individual work items take to move through the process.
**Why not D:** Daily coding time measures individual activity, not flow. Cycle time captures the full elapsed time for a work item from start to finish, including waiting, review, and testing.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).