CAPM Practice: Determine how to document project controls for an adaptive project
Question 31 of 60 in Determine how to document project controls for an adaptive project
What information does a cumulative flow diagram (CFD) provide for adaptive project controls?
Show answer & explanation
Correct answer: The distribution of work items across workflow states over time, revealing bottlenecks and cycle time
Explanation
A CFD shows how work items flow through stages (Backlog, In Progress, Done) over time. Widening bands indicate bottlenecks, and the vertical distance between bands shows work in progress.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).