Skip to content
CAPMMedium

CAPM Practice: Determine how to document project controls for an adaptive project

Question 31 of 60 in Determine how to document project controls for an adaptive project

What information does a cumulative flow diagram (CFD) provide for adaptive project controls?
Show answer & explanation

Correct answer: The distribution of work items across workflow states over time, revealing bottlenecks and cycle time

Explanation

A CFD shows how work items flow through stages (Backlog, In Progress, Done) over time. Widening bands indicate bottlenecks, and the vertical distance between bands shows work in progress.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free