CAPM Practice: Determine how to document project controls for an adaptive project
Question 31 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The distribution of work items across workflow states over time, revealing bottlenecks and cycle time
Explanation
A CFD shows how work items flow through stages (Backlog, In Progress, Done) over time. Widening bands indicate bottlenecks, and the vertical distance between bands shows work in progress.
**Why not A:** Defects found per iteration is a quality metric, not what a CFD displays. A CFD tracks the number of work items in each workflow state over time.
**Why not C:** Budget spent versus budget planned is a cost performance measure, not something shown on a CFD, which tracks work items through workflow states.
**Why not D:** A CFD shows the flow of work for the team as a whole, not individual team member productivity.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).