CAPM Practice: Determine how to document project controls for an adaptive project
Question 34 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Through backlog items (risk-adjusted stories) and discussed regularly in team ceremonies
Explanation
In adaptive projects, risks are often captured as backlog items or discussed in retrospectives and planning events. The iterative nature means risks are frequently revisited and addressed incrementally rather than in a separate formal process.
**Why not A:** A separate plan needing executive approval is a heavyweight predictive approach.
**Why not B:** Adaptive projects still capture risks; they just revisit them often.
**Why not D:** Monthly updates by the project manager alone are too infrequent and not team-owned.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).