CAPM Practice: Determine how to document project controls for an adaptive project

Question 56 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

Which meeting in Scrum is specifically designed to improve the team's process and ways of working?
Show answer & explanation

Correct answer: Sprint Retrospective

Explanation

The Sprint Retrospective is the team's dedicated improvement event. The team inspects how they worked (process, tools, relationships) and creates a concrete improvement plan for the next Sprint.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).