CAPM Practice: Determine how to document project controls for an adaptive project

Question 57 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

How should adaptive project teams document architectural decisions to avoid losing institutional knowledge?
Show answer & explanation

Correct answer: Use Architecture Decision Records (ADRs) — lightweight documents capturing the context, decision, and consequences of key architectural choices

Explanation

Architecture Decision Records (ADRs) are a lightweight, just-enough approach to capturing key technical decisions. They preserve the reasoning behind decisions without imposing heavyweight documentation overhead.

**Why not A:** Documents that are never updated become stale.

**Why not B:** Agile favors just-enough documentation, not none.

**Why not C:** Formal UML under change control is heavyweight overhead.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).