CAPM Practice: Determine how to document project controls for an adaptive project
Question 55 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The percentage of defects discovered by customers after release, indicating quality control effectiveness
Explanation
Escaped defect rate tracks defects found by end users post-release. A high escaped defect rate indicates that the team's in-iteration quality controls (testing, reviews) are insufficient to catch issues before shipping.
**Why not A:** Unfixed minor defects are deferred work, not defects that escaped to customers.
**Why not B:** This is a literal misreading of the term; it has nothing to do with developers.
**Why not D:** Defects found at Sprint Review are caught before release, so they have not escaped.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).