CAPM Practice: Determine how to document project controls for an adaptive project
Question 54 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Map existing control artifacts to agile equivalents and gradually reduce unnecessary reporting as trust builds
Explanation
A gradual transition — mapping Gantt charts to release roadmaps, status reports to sprint reviews, etc. — builds trust with stakeholders while eliminating unnecessary waste over time. Abrupt elimination causes disruption and resistance.
**Why not B:** Immediately eliminating all documentation and reporting removes stakeholders' visibility before trust in the new approach exists. This abrupt change causes disruption and resistance.
**Why not C:** Running full predictive and agile control systems in parallel indefinitely doubles the reporting burden and never removes the unnecessary waste the transition is meant to remove.
**Why not D:** Waiting until all staff are fully trained delays the transition indefinitely. Teams learn adaptive practices by applying them gradually, not by postponing every change until training is complete.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).